Zn Load & Unload Project
Project Description:
Sacré-Davey provided full detailed engineering for a truck and a rail loading facility to receive, stockpile and ship zinc concentrate at Kinder Morgan’s terminal in North Vancouver. Sacré-Davey completed the design of two dust collection and control systems to be installed in separate storage sheds
Challenges:
Brownfield design and construction.
Reduction of dust throughout the building, specifically around the zinc conveyor unloading, movement and truck loading.
SOLUTIONS:
Structural analysis of existing building and foundation calculations.
Innovative dust collection point source analysis and external baghouse.
ACHIEVEMENTS:
Truck routing and dust collection within design specifications.
Project completed within budget and schedule.