Phosrock Project
Project Description:
This Neptune Bulk Terminals facility improvement project required the installation of dry bulk ship unloading machinery, a network of inbound conveyors, a storage shed, and a network of outbound conveyors including a surge bin and a rail car load out system. A number of large dust collectors were also required to ensure that fugitive dust was captured.
Scope of Work:
As part of the engineering, procurement and construction team, Sacré-Davey assisted in this design build contract by taking the conceptual design through to final installation. Sacré-Davey’s scope included the detailed design of structures and select elements of the mechanical system such as the dust collector.
Project Solutions:
Structural analyses of foundation for the prefabricated steel storage building
Conveyor supports and transfer towers design
Steel and foundations design
Rail car loading steel structure and foundations
Dust collection towers and foundations design, including re-use of one transfer tower
Project Achievements:
Dust collection system.
Commissioning on schedule and operated to the owner specifications.