Other+Industries+Services.jpg

Studies, Compliance & Documentation

  • System gap analysis to ISO 55000

  • CMMS/EAM reviews

  • Equipment availability, productivity and OEE

  • Risk-based inspections (API 580)

  • Seismic assessments

  • Corrosion assessments

  • Energy efficiency studies

  • New plant design reviews

  • AACE cost estimating

  • HAZOP/HAZID studies handling

  • ISO 50001 readiness review

  • Audits energy management information systems (EMIS)

  • Plant-wide energy audits (electricity and natural gas)

  • Pre-feasibility and feasibility studies

  • Hydrogen risk assessment & safety analysis

Pulp &
Paper

  • Chips, sawdust, hog, chemicals

  • Groundwood, kraft and sulphite cycles

  • Digester area

  • Refining, TMP, CTMP, BCTMP

  • Brownstock washing and stock prep

  • Bleach plant and hi-density storage

  • Black liquor handling, concentration

  • Steam plant, recovery and power boilers

  • Green/white liquor handling and recausticizing

  • Steam cycles, recovery, use and reduction

  • Power generation and turbines

  • Pulp/paper machine

  • Dust control

Northern
Remote Sites

  • Sacré-Davey Engineering is equipped to design and operate in arctic environments for the following services:

    • Project management

    • Process engineering

    • Mechanical engineering

    • Energy management

    • Civil engineering

    • Structural engineering

    • Electrical engineering

  • To read more about our services, click the link below:

Food &
Beverage

  • Capacity studies and debottlenecking

  • Plant utility studies & evaluations

  • Product and raw material storage

  • Bulk materials handling systems

  • Process & layout modeling

  • Process optimization

  • Boilers, heating and refrigeration systems

  • Warehouse design & planning

  • Waste water collection & treatment

  • Dust collection systems

  • Plant commissioning/decommissioning

  • Energy management

  • H&S and food safety improvements

 

Past Projects

 

Studies, Compliance & Documentation

 

Zero Liquid
Discharge

Name of project: Zero Liquid DischargeType of Project: Capital Cost AssessmentOur Role: SDE was contracted to prepare a study and capital cost estimate for a water treatment system. Special Info: The study and engineering included a water …

Name of project: Zero Liquid Discharge

Type of Project: Capital Cost Assessment

Our Role: SDE was contracted to prepare a study and capital cost estimate for a water treatment system. 

Special Info: The study and engineering included a water balance for the entire facility, process and equipment selection, specification and budgetary equipment pricing for multiple equipment skids including a new building, interconnecting piping, foundations and road access.

Reclaim Barge Conditional Assessment

Name of project: Reclaim Barge Conditional AssessmentType of Project: Assessment of equipment functionalityOur Role: Sacre-Davey Engineering conducted NDT, visual inspections, a pump performance assessment and an investigation of the equipment …

Name of project: Reclaim Barge Conditional Assessment

Type of Project: Assessment of equipment functionality

Our Role: Sacre-Davey Engineering conducted NDT, visual inspections, a pump performance assessment and an investigation of the equipment historical and operational information.

Special Info: The client had concerns of two reclaim barges at their tailings pond site for both short and long term viability. The report allowed the client to make decisions with respect to Capex planning.

Design Review of Natural Gas Pipeline

Name of project: Design Review of Natural Gas PipelineType of Project: Design ReviewOur Role: SDE provided design review, stress analysis and design input for a 1000 PSIG, 20” diameter pipeline servicing the new gas plant in Northern BC.Sp…

Name of project: Design Review of Natural Gas Pipeline

Type of Project: Design Review

Our Role: SDE provided design review, stress analysis and design input for a 1000 PSIG, 20” diameter pipeline servicing the new gas plant in Northern BC.

Special Info: SDE’s input saved considerable cost and effort during the design phase by developing a file transfer protocol for importing client’s 3-D pipe model directly into Caesar for analysis. The timely analysis of different variation of the proposed pipe routing also saved considerable costs at road crossings and equipment tie-in locations.

Piping Integrity
Assessment

Name of project: Piping Integrity AssessmentType of Project: Integrity AssessmentOur Role: SDE completed an integrity assessment on steam, condensate, chloride, brine, and slurry piping systems within the process plant.Special Info: Sacré-Davey…

Name of project: Piping Integrity Assessment

Type of Project: Integrity Assessment

Our Role: SDE completed an integrity assessment on steam, condensate, chloride, brine, and slurry piping systems within the process plant.

Special Info: Sacré-Davey Engineering reviewed the piping systems to identify leaks, wall thinning, vibrations, misalignment, missing supports and poor practices. A comprehensive list of recommended repairs and replacements was provided.

 

Pulp & Paper

 

No. 2 Paper Machine Fourdrinier Table Rebuild

Project Name: No. 2 Paper Machine Fourdrinier Table Rebuild Client Name: Port Townsend Paper Corp. Industry Sector: Pulp & Paper Location: Washington, United States Project Description: This project includes the detailed design for the No. 2 pap…

Project Name: No. 2 Paper Machine Fourdrinier Table Rebuild

Client Name: Port Townsend Paper Corp.

Industry Sector: Pulp & Paper

Location: Washington, United States

Project Description: This project includes the detailed design for the No. 2 paper machine fourdrinier table rebuild at Port Townsend Paper. Sacré-Davey staff reviewed the documentation provided by the technology provider, IBS, and integrated the system requirements within the mill. We provided a scope of work construction package that described and detailed the multidisciplinary work and specific requirements for contractor installation.

Scope of Work: The SDE engineering team produced an IFC (issued for construction) package that included all work necessary to install ancillary equipment for proper operation of the rebuilt fourdrinier table. This included process, mechanical, electrical and instrumentation/control.

Challenges: Paper mill turnarounds are extremely important time periods each year for installation projects. As this project impacted a very important financial asset of the facility, Sacré-Davey was asked to carefully design around PM2's operations to make full use of the time period before and after the mill's outage.

A secondary challenge was utilizing the limited wet end spacing for installation of larger and more complex equipment configurations.

Solutions: As part of our scope of work packages, SDE deliberately separated the pre-outage work into its own standalone package, facilitating contractors to begin the construction/demo work weeks ahead of the turnaround. Additionally, SDE designed a more vertically integrated mechanical system that could be fabricated as a full system off-site and installed in place via crane.

Achievements: Sacre-Davey Engineering successfully compiled all aspects of the design packages utilizing 3D modeling software, multidisciplinary pulp and paper expertise, and mill management/operator communication to successfully install the fourdrinier rebuild.

RO Demineralization
Replacement

Project Name: Multimedia Filtration and Reverse Osmosis (RO) Water Demineralization Replacement System  Client Name: Port Townsend Paper Corp. Industry Sector: Pulp & Paper Location: Washington, United States Project Description: Port Townsend P…

Project Name: Multimedia Filtration and Reverse Osmosis (RO) Water Demineralization Replacement System

Client Name: Port Townsend Paper Corp.

Industry Sector: Pulp & Paper

Location: Washington, United States

Project Description: Port Townsend Paper had an in-situ separate train demineralizer water system feeding three separate boilers. Their system was old, unreliable, and prohibitive repair and maintenance costs facilitated a full system replacement. A technology provider was selected to provide a single pass system capable of flows from 500 to 800gpm. Sacre-Davey’s primary scope of work was integration of these units within the mill and detailed design for ancillary system requirements.

Scope of Work: The SDE engineering team produced an IFC (issued for construction) package that included all work necessary to demolish existing systems and install each new equipment skid (activated carbon filters, sand filters, and reverse osmosis) for proper operation of the demineralization process. This included process, mechanical/piping, structural, electrical and instrumentation + controls.

Challenges: Two adjacent rooms were selected by the mill to place the equipment skids as the existing system was still in operation. Site investigation confirmed that the rooms were very small for the size of the skids and that they had very limited structural support. Limited room meant additional pipe routing and instrument location challenges for the engineering team.

A secondary challenge was to provide an in parallel commissioning, start-up and “hot” switchover plan.

A secondary challenge was utilizing the limited wet end spacing for installation of larger and more complex equipment configurations.

Solutions: SDE’s solution was two-fold: provide an accurate and representative 3D model to isolate and identify interferences and relocate smaller equipment to adjacent unused areas maximizing room spacing. Helical piles were specified to support the 100-year-old floor and where piles could not physically be installed, structural foam was employed.

Additionally, SDE utilized previous hot switchover experience to schedule tie-in activities and provide operations with detailed step-by- step procedures.

Achievements: Sacre-Davey Engineering successfully completed all aspects of the design packages utilizing 3D modeling software, multidisciplinary industrial boiler feedwater expertise, and mill management/operator communication to successfully provide an integration solution for the demineralization replacement system.

65MW Cogen
Turbine

Project Name: 65MW Cogen Turbine Project Description: Mechanical and process design for 65 MW steam condensing turbine with 3 extraction stages, including extensive modifications to steam distribution network throughout the plant and rationalization…

Project Name: 65MW Cogen Turbine

Project Description: Mechanical and process design for 65 MW steam condensing turbine with 3 extraction stages, including extensive modifications to steam distribution network throughout the plant and rationalization of steam end use. Our pulp and paper client identified an opportunity to optimize steam resources and increase revenue by installing a 65 MW condensing steam turbine/generator set. Mill wide steam consumption was reviewed and maximum efficiency gained by converting several turbine drives to electric; optimizing steam generating boilers; and installing the turbine generator & associated equipment.

Scope of Work: The scope of the TG project involved turbine, new condenser, new mill-wide steam piping, cooling towers, electrical switchgear, controls, engineering and implementation assistance.
SDE and Binnington Development Corporation collaborated to provide definition level engineering services to develop preliminary process design and cost estimate for this project. Work included purchase and installation of a TG set and ancillary equipment; process control systems; grid interconnection and protection, major switchgear and substation. Work was completed on an EPCM basis for the equipment specification & procurement, detailed process, mechanical, electrical, instrumentation and controls engineering, as well as ongoing project/construction management support.

 

Northern Remote Sites

 

Igloolik Bulk Fuel Depot Upgrade

Name of project: Igloolik Bulk Fuel Depot UpgradeClient: Government of NunavutOur Role: Plans, specifications, project administration and site visits. In-office services during construction.Project Cost: $4.9M

Name of project: Igloolik Bulk Fuel Depot Upgrade

Client: Government of Nunavut

Our Role: Plans, specifications, project administration and site visits. In-office services during construction.

Project Cost: $4.9M

Building Foundations in Continuous Permafrost

Name of project: Building Foundations in Continuous PermafrostClient: Canadian RoyaltiesOur Role: Study of foundation solutions. Plans and specifications for foundations on thermosiphons for the mine buildings. Design of building mechanical, st…

Name of project: Building Foundations in Continuous Permafrost

Client: Canadian Royalties

Our Role: Study of foundation solutions. Plans and specifications for foundations on thermosiphons for the mine buildings. Design of building mechanical, structural & electrical power generation.

Design of the concentrator for the diesel plant, maintenance garage and housing units.

Project Cost: $250M

PCSP
Resolute

Name of project: PCSP ResoluteClient: Public Works and Government Services Canada for NRCanOur Role: Plans, specifications, construction supervision and commissioning for mechanical upgrades and extension to PCSP installations in Resolute, NU.P…

Name of project: PCSP Resolute

Client: Public Works and Government Services Canada for NRCan

Our Role: Plans, specifications, construction supervision and commissioning for mechanical upgrades and extension to PCSP installations in Resolute, NU.

Project Cost: $7M

Iqaluit
Airport

Name of project: Iqaluit AirportClient: Government of NunavutOur Role: Part of the Owner’s Technical Team. Preparation of tender documents for the new Airport Terminal Building and Combined Services Building.

Name of project: Iqaluit Airport

Client: Government of Nunavut

Our Role: Part of the Owner’s Technical Team. Preparation of tender documents for the new Airport Terminal Building and Combined Services Building.

 

Food & Beverage

 

Steam Supply
Upgrade

Name of project: Steam Supply UpgradeClient: Okanogan Spring BrewersType of Project: Equipment upgradeOur Role: Designing state of the art steam generators to replace old fire tube boilersServices Used: multi-disciplinary engineering

Name of project: Steam Supply Upgrade

Client: Okanogan Spring Brewers

Type of Project: Equipment upgrade

Our Role: Designing state of the art steam generators to replace old fire tube boilers

Services Used: multi-disciplinary engineering

Conveyer
Line

Name of project: Conveyer LineClient: Okanogan Spring BreweryType of Project: Design and retrofitOur Role: integrate new feed conveyer and palletizer into existing bottling lineServices Used: Multi-disciplinary engineering, construction managem…

Name of project: Conveyer Line

Client: Okanogan Spring Brewery

Type of Project: Design and retrofit

Our Role: integrate new feed conveyer and palletizer into existing bottling line

Services Used: Multi-disciplinary engineering, construction management, comissioning

Bakery
Decommission

Name of project: Engineering and project management of bakery decommissionType of Project: Bakery DecommissionOur Role: provided consultancy and project management from concept to completion, including: Scope definition and cost estimating, thr…

Name of project: Engineering and project management of bakery decommission

Type of Project: Bakery Decommission

Our Role: provided consultancy and project management from concept to completion, including:

  • Scope definition and cost estimating, through discussions with client and negotiations with the landlord.

  • Removal of the equipment for use in other facilities, for sale or for scrap.

  • Building repairs and modifications as per agreed upon scope with client and landlord.

  • Final reviews and approvals with client, landlord and authorities

Services Used: Multi-disciplinary engineering, consultancy, project management

Dough Mixer Refrigeration System Glycol

Name of project:  Dough Mixer Refrigeration System Glycol Type of Project: Design and installationOur Role: Provided consultancy and project management from concept to completion, including:Design and construction of an addition to the existing…

Name of project:  Dough Mixer Refrigeration System Glycol

Type of Project: Design and installation

Our Role: Provided consultancy and project management from concept to completion, including:

  • Design and construction of an addition to the existing building to accommodate the new Glycol system.

  • Installation of the new Glycol system, including Glycol tank, pumps, control panel, pipes, valves and tie in to the existing Mixers and compressors.

  • Complete overhaul of the Bread mixers and replacement of the dough bowls and refrigeration jackets.

  • Design and installation of the temporary reinforcements and shoring of the existing elevated concrete floor slab during installation.

Services Used: Multi-disciplinary engineering, consultancy, project management