Phosrock Unloading, Loading & Storage

phosrock unloading

This Neptune Bulk Terminals facility improvement project for phosrock unloading, loading and storage required the installation of dry bulk ship unloading machinery, network of inbound conveyors, a storage shed, a network of outbound conveyors including a surge bin and a rail car load out system. Due to environmental concerns, a number of large dust collectors were required to ensure that fugitive dust was captured.

As part of the engineering, procurement and construction team, SDE assisted in this design build contract in taking a conceptual design through to final installation. SDE’s scope included the detailed design of structures and select elements of the mechanical system such as the dust collector.