New 50% Hydrogen Peroxide Receiving And Distribution System

Norske Canada required a new peroxide unloading, makedown and distribution facility to enable them to receive railcars in lieu of tanker trucks. The project included new foundations, tank design, spill containment, as well as pumping and piping systems. Previously estimated by others at $1.2M for the new plant, SDE/SN worked with facility owners to complete the project for under $700K.

SDE provided project estimating, conceptual and detailed design, and some procurement. Our associate, Solutions Now (SN) provided project management services.